{"requirement_id":"JDDG25-14.13-R02","source":{"document":"Japan District Design Guide","version":"9.0","publication_date":"2025-04","chapter":"14","section":"14.13","title":"SEISMIC DESIGN REQUIREMENTS (OF ELECTRICAL SYSTEMS)","page_printed":280,"page_pdf":310,"fact":"Designated Seismic Systems should be identified in the Statement and Schedule of Special Inspections; examples include switchgear, panels, emergency fixtures, UPS, and inverters.","modality":"imperative","strength":"mandatory"},"localization_ja":{"language":"ja","title_ja":"電気系統の耐震設計要件","title_status":"controlled_editorial","fact_ja":null,"fact_translation_status":"pending","modality_rendering_ja":"～すること","strength_label_ja":"必須","translation_priority":"high","translation_notes":[],"title_translation_provenance":"editorial_controlled","fact_translation_provenance":"not_translated","publication_eligible":false},"references":["IBC 2018 1705.12.4"],"meaning":{"engineering_basis":null,"engineering_basis_source":null,"engineering_interpretation":null,"interpretation_confidence":null},"risk":{"failure_modes":[],"failure_mode_source":"not_stated","failure_domains":[]},"quality":{"source_status":"normal","data_quality_flag":"normal"},"applicability":{"applicability_class":"general","evaluation_mode":"default_applicable","evaluation_scope":"project","input_semantics":"none","source_condition_text":null,"trigger":null,"approval_gate":null,"exception_condition":null,"condition_provenance":"none","normalization_provenance":"none"},"lifecycle":{"primary_phase":"commissioning","primary_phase_label":"Testing / Commissioning / Acceptance","applicable_phases":["design","commissioning"],"phase_links":[{"phase":"design","provenance":"jddg_cross_section_explicit","basis":"Linked to separate JDDG Section 14.8 design evidence/submittal requirements.","phase_label":"Design"},{"phase":"commissioning","provenance":"source_explicit","basis":"Source explicitly requires testing, measurement, inspection, or acceptance performance.","phase_label":"Testing / Commissioning / Acceptance"}]},"responsibility":{"primary_workflow_owner":"ACT-DESIGNER-AE","primary_workflow_owner_name":"Designer / A-E","actor_assignment_status":"workflow_only","actors":[{"actor_id":"ACT-DESIGNER-AE","actor_name":"Designer / A-E","actor_class":"project_delivery","source_named":true,"relation_type":"workflow_owner","provenance":"editorial_derived","lifecycle_phase":"design","lifecycle_phase_label":"Design","basis":"Workflow owner assigned from lifecycle phase for checklist routing; not a contractual responsibility statement."},{"actor_id":"ACT-WORKFLOW-VERIFICATION-PARTY","actor_name":"Verification / Testing Party (Workflow Placeholder)","actor_class":"workflow_placeholder","source_named":false,"relation_type":"workflow_owner","provenance":"editorial_derived","lifecycle_phase":"commissioning","lifecycle_phase_label":"Testing / Commissioning / Acceptance","basis":"Workflow owner assigned from lifecycle phase for checklist routing; not a contractual responsibility statement."}]},"verification":{"method":"special_inspection_document_review","stage":["design"],"acceptance_criteria":null,"evidence_required":["statement_of_special_inspections","schedule_of_special_inspections"],"verification_provenance":"editorial_derived","evidence_provenance":"jddg_cross_section_explicit","audit_status":"derived_check_method_not_stated_by_source","audit_confidence":"medium","acceptance_provenance":"not_stated_in_jddg","evidence_type_ids":["EV-DESIGN-ANALYSIS-FINAL","EV-SEISMIC-CALC","EV-PRODUCT-DATA","EV-FINAL-CALCULATIONS","EV-FINAL-DRAWINGS"],"supporting_source_requirements":["JDDG25-14.8.4.3-R01","JDDG25-14.8.3.3-R05","JDDG25-14.8.2.3-R04","JDDG25-14.8.3.1-R02","JDDG25-14.8.4.3-R02","JDDG25-14.8.4.1-R01","JDDG25-14.8.4.1-R03"],"source_support_scope":"design_submittal_or_analysis"},"resolved_evidence":[{"evidence_type_id":"EV-DESIGN-ANALYSIS-FINAL","name":"Final Design Analysis compliance verification","source_requirement_ids":["JDDG25-14.8.4.3-R01"],"stage":["final_design"],"source_scope":"Final Design Analysis should support and verify design compliance with project requirements."},{"evidence_type_id":"EV-SEISMIC-CALC","name":"Seismic-protection calculations","source_requirement_ids":["JDDG25-14.8.3.3-R05"],"stage":["intermediate_design"],"source_scope":"JDDG identifies qualified professionals who may perform seismic-protection calculations."},{"evidence_type_id":"EV-PRODUCT-DATA","name":"Major equipment product data / datasheets","source_requirement_ids":["JDDG25-14.8.2.3-R04","JDDG25-14.8.3.1-R02"],"stage":["concept_design","intermediate_design"],"source_scope":"Design analysis/detail sheets include product data and salient characteristics for proposed major equipment."},{"evidence_type_id":"EV-FINAL-CALCULATIONS","name":"Final engineering calculations","source_requirement_ids":["JDDG25-14.8.4.3-R02"],"stage":["final_design"],"source_scope":"All final calculations are included in the Final Design Analysis."},{"evidence_type_id":"EV-FINAL-DRAWINGS","name":"Final contract drawings and details","source_requirement_ids":["JDDG25-14.8.4.1-R01","JDDG25-14.8.4.1-R03"],"stage":["final_design"],"source_scope":"Final drawings contain required details and are checked for discrepancies and interdisciplinary compatibility."}],"supporting_source_requirements":[{"requirement_id":"JDDG25-14.8.4.3-R01","section":"14.8.4.3","title":"DESIGN ANALYSIS","fact":"Final design analysis should support and verify that the design complies with project requirements."},{"requirement_id":"JDDG25-14.8.3.3-R05","section":"14.8.3.3","title":"DESIGN ANALYSIS","fact":"Seismic-protection calculations may be performed by a registered U.S. engineer or a Japanese 1st Class Qualified Architect."},{"requirement_id":"JDDG25-14.8.2.3-R04","section":"14.8.2.3","title":"DESIGN ANALYSIS","fact":"Concept Design Analysis appendices should include product data for proposed major electrical equipment, using Japanese product data to the greatest extent possible particularly for luminaires."},{"requirement_id":"JDDG25-14.8.3.1-R02","section":"14.8.3.1","title":"DRAWINGS","fact":"Chosen systems and equipment should be detailed with dimensions, salient characteristics, and related notes."},{"requirement_id":"JDDG25-14.8.4.3-R02","section":"14.8.4.3","title":"DESIGN ANALYSIS","fact":"All final calculations are to be included in the Final Design Analysis."},{"requirement_id":"JDDG25-14.8.4.1-R01","section":"14.8.4.1","title":"DRAWINGS","fact":"Final drawings should contain all details required for the final package."},{"requirement_id":"JDDG25-14.8.4.1-R03","section":"14.8.4.1","title":"DRAWINGS","fact":"Final drawings are to be checked for discrepancies and compatibility with specifications and other disciplines."}],"references_resolved":[{"source_reference_text":"IBC 2018 1705.12.4","reference_id":"EXT-IBC-2018","scope":"external","reference_type":"code","document_number":"IBC 2018","locator":"1705.12.4","dependency_type":"supporting_or_compliance_reference","title":null,"chapter_criteria_listed":false,"quality_flags":[],"external_content_status":"not_ingested"}]}