{"requirement_id":"JDDG25-14.8.2.1-R03","source":{"document":"Japan District Design Guide","version":"9.0","publication_date":"2025-04","chapter":"14","section":"14.8.2.1","title":"DRAWINGS","page_printed":238,"page_pdf":268,"fact":"Concept drawings are to identify demolition and installation delineation points for exterior feeders, transformers, manholes/handholes, grounding, switchgear, lighting, and associated equipment.","modality":"imperative","strength":"mandatory"},"localization_ja":{"language":"ja","title_ja":"図面","title_status":"controlled_editorial","fact_ja":null,"fact_translation_status":"pending","modality_rendering_ja":"～すること","strength_label_ja":"必須","translation_priority":"high","translation_notes":[],"title_translation_provenance":"editorial_controlled","fact_translation_provenance":"not_translated","publication_eligible":false},"references":[],"meaning":{"engineering_basis":null,"engineering_basis_source":null,"engineering_interpretation":null,"interpretation_confidence":null},"risk":{"failure_modes":[],"failure_mode_source":"not_stated","failure_domains":[]},"quality":{"source_status":"normal","data_quality_flag":"normal"},"applicability":{"applicability_class":"general","evaluation_mode":"default_applicable","evaluation_scope":"project","input_semantics":"none","source_condition_text":null,"trigger":null,"approval_gate":null,"exception_condition":null,"condition_provenance":"none","normalization_provenance":"none"},"lifecycle":{"primary_phase":"design","primary_phase_label":"Design","applicable_phases":["design","design/concept","installation"],"phase_links":[{"phase":"design","provenance":"source_explicit","basis":"Source explicitly assigns a designer/design-document action.","phase_label":"Design"},{"phase":"design/concept","provenance":"source_explicit","basis":"Section 14.8.2 is Concept Design.","phase_label":"Concept Design"},{"phase":"installation","provenance":"source_implied","basis":"Source requirement concerns installed configuration or physical construction.","phase_label":"Installation / Construction"}]},"responsibility":{"primary_workflow_owner":"ACT-DESIGNER-AE","primary_workflow_owner_name":"Designer / A-E","actor_assignment_status":"workflow_only","actors":[{"actor_id":"ACT-DESIGNER-AE","actor_name":"Designer / A-E","actor_class":"project_delivery","source_named":true,"relation_type":"workflow_owner","provenance":"editorial_derived","lifecycle_phase":"design","lifecycle_phase_label":"Design","basis":"Workflow owner assigned from lifecycle phase for checklist routing; not a contractual responsibility statement."},{"actor_id":"ACT-DESIGNER-AE","actor_name":"Designer / A-E","actor_class":"project_delivery","source_named":true,"relation_type":"workflow_owner","provenance":"editorial_derived","lifecycle_phase":"design/concept","lifecycle_phase_label":"Concept Design","basis":"Workflow owner assigned from lifecycle phase for checklist routing; not a contractual responsibility statement."},{"actor_id":"ACT-CONSTRUCTION-CONTRACTOR","actor_name":"Construction Contractor","actor_class":"project_delivery","source_named":true,"relation_type":"workflow_owner","provenance":"editorial_derived","lifecycle_phase":"installation","lifecycle_phase_label":"Installation / Construction","basis":"Workflow owner assigned from lifecycle phase for checklist routing; not a contractual responsibility statement."}]},"verification":{"method":"design_and_installation_conformance_review","stage":["design","installation"],"acceptance_criteria":null,"evidence_required":["design_document_or_installed_condition"],"verification_provenance":"editorial_derived","evidence_provenance":"jddg_cross_section_explicit","audit_status":"derived_check_method_not_stated_by_source","audit_confidence":"medium","acceptance_provenance":"not_stated_in_jddg","evidence_type_ids":["EV-EXTERIOR-ELECTRICAL-PLAN","EV-FINAL-DRAWINGS"],"supporting_source_requirements":["JDDG25-14.8.2.1-R03","JDDG25-14.8.3.1-R04","JDDG25-14.8.4.1-R01","JDDG25-14.8.4.1-R03"],"source_support_scope":"design_submittal_or_analysis"},"resolved_evidence":[{"evidence_type_id":"EV-EXTERIOR-ELECTRICAL-PLAN","name":"Exterior electrical plan","source_requirement_ids":["JDDG25-14.8.2.1-R03","JDDG25-14.8.3.1-R04"],"stage":["concept_design","intermediate_design"],"source_scope":"Exterior plans identify work delineation and electrical characteristics of equipment."},{"evidence_type_id":"EV-FINAL-DRAWINGS","name":"Final contract drawings and details","source_requirement_ids":["JDDG25-14.8.4.1-R01","JDDG25-14.8.4.1-R03"],"stage":["final_design"],"source_scope":"Final drawings contain required details and are checked for discrepancies and interdisciplinary compatibility."}],"supporting_source_requirements":[{"requirement_id":"JDDG25-14.8.2.1-R03","section":"14.8.2.1","title":"DRAWINGS","fact":"Concept drawings are to identify demolition and installation delineation points for exterior feeders, transformers, manholes/handholes, grounding, switchgear, lighting, and associated equipment."},{"requirement_id":"JDDG25-14.8.3.1-R04","section":"14.8.3.1","title":"DRAWINGS","fact":"Intermediate exterior electrical drawings are to identify electrical characteristics for all electrical items, including voltage, phase, size, frequency, and kVA."},{"requirement_id":"JDDG25-14.8.4.1-R01","section":"14.8.4.1","title":"DRAWINGS","fact":"Final drawings should contain all details required for the final package."},{"requirement_id":"JDDG25-14.8.4.1-R03","section":"14.8.4.1","title":"DRAWINGS","fact":"Final drawings are to be checked for discrepancies and compatibility with specifications and other disciplines."}],"references_resolved":[]}