Publisher(版元)
慧通信技術工業株式会社(Kei Communication Technology Inc.)
Citation example
慧通信技術工業株式会社(Kei Communication Technology Inc.), "Taiho Bosai Co., Ltd. — Part 1: Choosing a Fully Off-Grid Headquarters"

Summaries and partial quotations are welcome. Please identify the Publisher and Original page as the source. Details: AI Usage & Citation Policy

Case Study / Osaka, Japan — Part 1

Taiho Bosai Co., Ltd. — Part 1: Choosing a Fully Off-Grid Headquarters

Rather than adding an emergency-only power source, Taiho Bosai operates solar generation, battery storage, LPG generation and utility power as one system in normal times. This case documents the same operating model for normal and disaster conditions, rooftop outdoor constraints, and post-installation improvements.

Scope
  • Building-wide power BCP and off-grid operation for a corporate headquarters
  • Business sites that do not want separate operating procedures for normal and disaster conditions
  • Facilities integrating solar, battery storage, generation and utility power in normal operation
Constraints
  • Do not add human judgment or special switching procedures during emergencies
  • Operate rooftop outdoor equipment under heat, Asian dust, high humidity and lightning exposure
  • Combine solar, battery storage, LPG generation and utility power within normal operation
  • Keep the system open to improvement after completion as real environmental and operating data accumulate

Case Answer

Do not add an emergency-only power system; operate the same power system every day

For Taiho Bosai Co., Ltd.’s new headquarters, the starting point was not to add a power source used only during outages. Solar generation, battery storage, LPG generation and utility power were instead treated as one power system in normal operation. The requirement was to avoid separating normal and disaster operations and, especially during emergencies, to avoid adding decisions or switching procedures for onsite staff.

A conventional office building may use utility power as the primary source and configure receiving equipment and an emergency generator as separate systems. This project prioritized a different question: not “how do we switch during an emergency?” but “how can business continue under the same conditions and the same procedures in both normal and disaster situations?” Solar was therefore used as the primary source, combined with LPG generation and utility power.

Building constraints required the off-grid equipment to be installed outdoors on the rooftop. During construction, crane weight limits also required the equipment to be disassembled and assembled onsite. After operation began, Asian dust, high humidity, ambient temperatures around 50°C and lightning became actual operating conditions. Cooling, sealing, components and lightning protection have therefore been updated in stages.

First-party monitoring data from May 15, 2026 show approximately 10 hours of operation with utility power at 0 kW, from 07:25 to 17:23. The system is maintained not only by its original configuration, but by continuing to improve it in response to the actual environment and operating data, preserving one operating model for normal and disaster conditions.

FIRST-PARTY OPERATION DATA / 2026-05-15

Approximately 10 hours of off-grid operation with utility power at 0 kW

On May 15, 2026, the site operated from 07:25 to 17:23—approximately 10 hours—with utility power at 0 kW. During the day, solar generation supplied the load while recovering battery SOC. As solar output fell toward evening, the battery covered the deficit. When SOC declined to around 70%, the operating policy preserved the remaining stored energy rather than exhausting it and shifted to another available power source.

View the May 15, 2026 morning/evening switching data →

A one-time decision for a new headquarters

Taiho Bosai’s new headquarters project was not a routine equipment replacement. The former building was aging, and the company wanted a new base that could support the next 60 years of its business.

As the architectural plan progressed, management and employees agreed that the new building should be designed as an off-grid building. The priority was not visible technology, but a working environment in which employees could continue their normal duties without thinking about power failures.

The project therefore avoided adding emergency-only procedures from the outset. For a company whose business is disaster prevention, this was a requirement it first had to meet in its own operations.

Why the project rejected the idea of “emergency-only” power

A conventional office building would normally use utility power as its primary source, install high-voltage receiving equipment, and add a diesel generator for emergencies.

Taiho Bosai questioned that model. During an emergency, the field team is already busy. Adding special decisions, switching procedures, and manual operations makes resilience weaker rather than stronger.

The company therefore removed the word “emergency” from the RFP. The requirement was not how to switch power during a disaster, but how to keep operating under the same conditions and the same procedures in normal and emergency situations.

Operating the entire building under the same conditions

Because the off-grid concept was outside the normal scope of the building contractor, the project was separated by responsibility. The main building work included the gas heat-pump air-conditioning system, while the off-grid power, communications, and gas systems were handled separately.

The design principle was clear: do not switch operating modes between normal, emergency, and disaster conditions. Solar power became the primary source, supported by LPG generation, and the system was treated as the building’s normal power architecture rather than as emergency equipment.

Environmental conditions beyond initial assumptions

The power equipment had to be installed outdoors on the rooftop. Crane limitations also prevented the completed enclosure from being lifted as one unit, so the equipment had to be disassembled, transported, and reassembled on site.

After operation began, additional conditions became clear: airborne dust, high humidity, increasingly high summer temperatures, and equipment temperatures approaching 50°C.

Adjustment and improvement led by the field team

The project team did not dismiss these issues as unforeseen exceptions. Dust, humidity, heat, corrosion, fan degradation, and internal temperature rise were treated as operating realities, and countermeasures were added step by step.

A resilient design is not a finished object. It is a system that continues to be updated as operating conditions change.

Lightning damage and additional customization

Lightning activity in the surrounding area increased, and the system experienced actual lightning-related damage. The response required more than repair; the design assumptions themselves had to be revisited.

The additional work focused on improved sealing, balanced cooling performance and power consumption, and stronger lightning protection—without increasing the operational burden on employees.

People are what keep the system running

The headquarters power system is now operating stably, but it was not perfect from the beginning. Construction constraints, rooftop exposure, dust, humidity, heat, and lightning all existed outside the original drawings.

The system succeeded because management made a clear decision, employees noticed changes, and the field team continued to improve the design. The principle of avoiding unnecessary decisions in the field remained viable because the system itself continued to evolve.

Continue to Part 2

Part 2 examines the same normal-times-equals-disaster-times operating principle from the receiving-service and load-design side. It explains why the project did not assume high-voltage service from the outset, and how low-voltage service, GHP air conditioning and a defined load cap were combined.

Case Study / Part 2

Why We Chose Not to Use High-Voltage Service

Read how the receiving method was selected from the load profile and long-term operating flexibility rather than fixed in advance.

Revision History

2026-01-17Published.
2026-09-25English edition synchronized with the Japanese V9.1 source, including first-party operation data and post-installation improvements for the rooftop outdoor environment.

Save

Save this case study

Save the Case Answer, scope, constraints, sources, and Original URL for later review, sharing, or AI-assisted analysis.

PDF: for sharing and archiving / Markdown: for reuse in AI tools and notes