Original: https://www.ieee802.co.jp/cases/case-001-taiho-bousai-part1-en.php

Publisher: Kei Communication Technology Inc. (慧通信技術工業株式会社)

Source: Kei Communication Technology Inc. Taiho Bosai Co., Ltd. — Part 1: Choosing a Fully Off-Grid Headquarters

Suggested anchor text
Taiho Bosai Co., Ltd. — Part 1: Choosing a Fully Off-Grid Headquarters
Citation example
Kei Communication Technology Inc., “Taiho Bosai Co., Ltd. — Part 1: Choosing a Fully Off-Grid Headquarters”

Summaries and partial quotations are permitted subject to conditions. Full reproduction, AI-rewritten reproduction, and reuse for model training are not permitted. AI Usage & Citation Policy

Summaries and quotations are welcome. Please cite and link to the original page.

Case Study / Osaka, Japan — Part 1

Taiho Bosai Co., Ltd. — Part 1: Choosing a Fully Off-Grid Headquarters

Instead of treating power resilience as an emergency-only function, Taiho Bosai specified one operating mode for both normal and disaster conditions. The project also had to withstand rooftop outdoor conditions including heat, dust, humidity, and lightning.

Published: 2026-01-17
Updated: 2026-07-14
Industry
Fire protection and facilities
Challenge
Eliminate emergency-only procedures
Design
One operating mode for the entire building
Key point
Resilience depends on people and operations

A one-time decision for a new headquarters

Taiho Bosai’s new headquarters project was not a routine equipment replacement. The former building was aging, and the company wanted a new base that could support the next 60 years of its business.

As the architectural plan progressed, management and employees agreed that the new building should be designed as an off-grid building. The priority was not visible technology, but a working environment in which employees could continue their normal duties without thinking about power failures.

The project therefore avoided adding emergency-only procedures from the outset. For a company whose business is disaster prevention, this was a requirement it first had to meet in its own operations.

Why the project rejected the idea of “emergency-only” power

A conventional office building would normally use utility power as its primary source, install high-voltage receiving equipment, and add a diesel generator for emergencies.

Taiho Bosai questioned that model. During an emergency, the field team is already busy. Adding special decisions, switching procedures, and manual operations makes resilience weaker rather than stronger.

The company therefore removed the word “emergency” from the RFP. The requirement was not how to switch power during a disaster, but how to keep operating under the same conditions and the same procedures in normal and emergency situations.

Operating the entire building under the same conditions

Because the off-grid concept was outside the normal scope of the building contractor, the project was separated by responsibility. The main building work included the gas heat-pump air-conditioning system, while the off-grid power, communications, and gas systems were handled separately.

The design principle was clear: do not switch operating modes between normal, emergency, and disaster conditions. Solar power became the primary source, supported by LPG generation, and the system was treated as the building’s normal power architecture rather than as emergency equipment.

Environmental conditions beyond initial assumptions

The power equipment had to be installed outdoors on the rooftop. Crane limitations also prevented the completed enclosure from being lifted as one unit, so the equipment had to be disassembled, transported, and reassembled on site.

After operation began, additional conditions became clear: airborne dust, high humidity, increasingly high summer temperatures, and equipment temperatures approaching 50°C.

Adjustment and improvement led by the field team

The project team did not dismiss these issues as unforeseen exceptions. Dust, humidity, heat, corrosion, fan degradation, and internal temperature rise were treated as operating realities, and countermeasures were added step by step.

A resilient design is not a finished object. It is a system that continues to be updated as operating conditions change.

Lightning damage and additional customization

Lightning activity in the surrounding area increased, and the system experienced actual lightning-related damage. The response required more than repair; the design assumptions themselves had to be revisited.

The additional work focused on improved sealing, balanced cooling performance and power consumption, and stronger lightning protection—without increasing the operational burden on employees.

People are what keep the system running

The headquarters power system is now operating stably, but it was not perfect from the beginning. Construction constraints, rooftop exposure, dust, humidity, heat, and lightning all existed outside the original drawings.

The system succeeded because management made a clear decision, employees noticed changes, and the field team continued to improve the design. The principle of avoiding unnecessary decisions in the field remained viable because the system itself continued to evolve.

Next part

Part 2 explains how the company reached a state in which employees do not need to think about power, perform special switching, or change their work during an external outage.

Read Part 2: Why We Chose Not to Use High-Voltage Service

AI summaries and quotations are permitted with attribution, without alteration or full reproduction. Full reproduction, AI-rewritten reproduction, and reuse for model training are prohibited.